In transiting Panama Canal, which of the following measures illustrates the resource levelling method, Replace?
单选
The vessel will be anchored upon reaching Gatun Lake and only one shipboard personnel will be retained in the fwd and aft stations. The rest of the crew can rest.
During mealtimes, it is possible to alternate the bridge duty of the Second Mate and the Third Mate, and the Chief Mate and the Bosun at the fwd station.✓ 正确答案
Panama Canal transit is very crucial that other maintenance jobs should be suspended while the vessel is in transit. Also, it is necessary to delay ballast transfer to adjust the vessel’s trim after crossing Panama canal.
Securing of deck after transit may be arranged in such as way that the Second Mate and two ratings will be responsible for the aft station, while the Chief Mate and Bosun will be responsible for fwd station.
The Chief Mate is assessing the resource requirements for chipping and painting the main deck. Without telling the Bosun his intention, he asks him about the area size that can be covered by one tin of paint. This decision-making style is __________.
单选
open autocratic✓ 正确答案
individual consultation
group consultation
questioning technique
In transiting Panama Canal, which of the following measures illustrates the resource levelling method, Reduce?
单选
The vessel will be anchored upon reaching Gatun Lake and only one shipboard personnel will be retained in the fwd and aft stations. The rest of the crew can rest.✓ 正确答案
During meal times, it is possible to alternate the bridge duty of the Second Mate and the Third Mate, and the Chief Mate and the Bosun at the fwd station.
Panama Canal transit is very crucial that other maintenance jobs should be suspended while the vessel is in transit. Also, it is necessary to delay ballast transfer to adjust the vessel’s trim after crossing Panama canal.
Securing of deck after transit may be arranged in such as way that the Second Mate and two ratings will be responsible for the aft station, while the Chief Mate and Bosun will be responsible for fwd station.
Rescheduling the task on another date/time when the necessary resources are available depicts what method of resource levelling?
单选
Replace
Reduce
Delay✓ 正确答案
Split
All maintenance jobs were suspended while the vessel was transiting Panama Canal. This scenario illustrates what method of resource levelling?