In replacing a defective transformer with a new one, which of the following actions must be carried out to insure proper operation of the equipment it serves?
单选
The secondary leads must be grounded for 10 minutes to remove static charges.
The transformer connections must be made as before with regard to the indicated polarity.✓ 正确答案
The iron core of the transformer must be flashed to pre-magnetize it.
The iron core must be grounded for 10 minutes to remove any residual magnetism.
Regarding battery charging rooms, ventilation should be provided
单选
at the lowest point of the room
horizontally near the batteries
at the highest point of the room✓ 正确答案
only when charging is in progress
You are attempting to parallel two AC generators and the synchroscope pointer is revolving slowly in the fast direction You should
单选
use the governor control switch to adjust the incoming voltage so it is equal to the bus voltage
use the governor control switch to increase the speed of the machine on the line only
close the circuit breaker when the synchroscope pointer approaches the 0° position✓ 正确答案
use the field rheostat to adjust the speed of the incoming machine
Which of the following temperatures represents the maximum allowable temperature for the electrolyte of a lead-acid battery?
单选
100°F
125°F✓ 正确答案
145°F
212°F
Maintenance of alkaline batteries should include
单选
checking the electrolyte weekly using a hydrometer
replacing the electrolyte every 5 years
trickle charging✓ 正确答案